Friday, April 15, 2016

Water Main Installed

Work Completed Last Week, April 11th to April 15th
·         Completed water main installation along Pine Street to East Lake Avenue
·         Installed water main in northerly cul-de-sac
·         Performed required testing of water main along Pine Point from Church Street to Pine Street.
Work Anticipated to be completed Next Week, April 18th to 22nd  
·         Continue with required testing of installed water main along entire project
·         Sanitary sewer repairs
·         Storm sewer repairs
·         Water service replacement 

The main line water main will be completed either on Friday or Monday of next week. Following water main installation, the contractor will perform the required testing and acquire the necessary approvals prior to placing the water main into service and starting to install water services to each individual home. Water service installation may begin near the end of the week.

Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 1 hour while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

Thank you again for all your patience and understanding throughout the construction operations and disruptions to water service.