Work Completed Last Week, May 9th to 13th
·
Completed water service replacements
·
Made final connections to existing water main at
Pine Point and Pine Court
·
Abandoned old fire hydrants and valves
·
Tree removal along East Lake Avenue
·
Started concrete curb & gutter removal
Work Anticipated to be completed Next Week, May 16th
to 20th
·
Complete concrete curb & gutter removal
·
Pour new concrete curb & gutter – Monday,
May 16th
·
Asphalt restoration of underground utility
trenches
·
Install fire hydrant near East Lake Avenue
·
Replace guard rail at Pine Point and Church
Street
·
Fence repair along East Lake Avenue
·
Grading and clean-up within vacant properties on
north side of Pine Street.
The underground utility improvement phase of the project is
nearly complete, with the exception of a few minor items. The roadway
improvement phase has now began.
Concrete curb & gutter removal and replacement is being
performed at select locations including areas damaged during construction,
generally poor condition, or to improve drainage. During the roadway
improvements phase, we ask that you do not park your cars along the street
during working hours to facilitate the construction operations. If your
driveway access will be restricted during the concrete replacement process, a
letter has been delivered providing details regarding schedule and parking
options. If you received a general letter stating concrete curb &
gutter replacement, your driveway access will not be restricted, but we
continue to ask you not to park on the street during working hours.
The contractor will also begin excavating the stone trenches
where the underground utility improvements were completed. This work is
anticipated to begin on Tuesday, May 17th. Again, we request you do
not park on the street during working hours. There may be a period of time when
access is not allowed due to the trench being excavated in front of your
driveway prior to the asphalt patch material being installed; however access
will be provided each night. The contractor will notify you prior to excavating
adjacent to driveways.
Once the contractor completes the concrete curb & gutter
replacement and trench paving, the amount of dust along the street should be
greatly reduced.
Landscape restoration with sod is anticipated to begin
within the next 2 weeks, with hopes of being completed prior to Memorial Day
weekend.
Thank you again for all your patience and understanding
during the numerous water shut-downs required during the duration of the water
main replacement portion of the project. Thank you in advance to those
residents who will be without driveway access during concrete curb & gutter
replacement.