Completed concrete curb & gutter removal and
replacement at select locations, excluding new cul-de-sac area at north end of
Pine Street
·
Installed new fire hydrant near East Lake Avenue
·
Rough graded landscape areas to be restored.
·
Asphalt driveway restorations
·
Excavate and remove existing roadway at the
north end of the project
·
Excavate and install aggregate base course for
new cul-de-sac and island on north end of Pine Street
·
Grading and clean-up with vacant properties on
north end of Pine Street
·
Complete excavation and installation of
aggregate base in new cul-de-sac on the north end of Pine Street
·
Pour concrete curb & gutter for cul-de-sac and
island on north end of Pine Street
·
Final grading, topsoil and sod installation
along project site.
·
Replace guard rail at Pine Point and Church
Street
·
Fence repair along East Lake Avenue
Thank you to those residents who were without driveway
access last week due to concrete curb & gutter replacement. Trench paving
has been delayed in order to complete the topsoil and sod landscape
restoration. The trench paving will be completed in conjunction with the
roadway resurfacing portion of the project.
Thanks again for all your patience as the construction
project continues through the roadway rehabilitation phase.