·
Milled existing asphalt surface along Pine
Street
·
Performed pavement patching as required along
existing roadway
·
Begin construction of earthen berm along East
Lake Avenue
·
Replaced guard rail at Pine Point and Church
Street
·
Performed final testing of new water main
Work Anticipated to be completed Next Week, June 6th
to June 10th
·
Pave asphalt surface along entire project
site
·
Complete construction of earthen berm along East
Lake Avenue
·
Plant trees on earthen berm
·
Sod restorations along Pine Street that were not
previously completed
·
Topsoil, seed, and erosion blanket restoration
along vacant properties on north end of Pine Street
·
Perform final walk-through with Village staff to
determine any outstanding items to be completed.
The major construction is nearing a completion with the installation
of the final asphalt surface layer scheduled for early next week. We request
vehicles are not parked along the street during working hours (7:00 AM to
5:00). Cars may be parked along the street during non-working hours.
On the day of final asphalt surface paving, we also request
trips along Pine Street are limited to help facilitate construction and provide
a better final product. Once the asphalt is rolled for the final time, vehicles
are allowed to drive on the roadway.
The morning of the asphalt surface paving, a thin layer of
tack coat (or oil) will be placed on the existing surface. This can be driven
over; however, we request you please drive slowly to help prevent the tack coat
from getting on your vehicles.
Thanks again for all your patience and understanding
throughout the entire construction project. We hope that you are satisfied with
the overall project and improvements made to your neighborhood.