Friday, June 17, 2016

Project Completed!!!!

The Pine Street Improvement project is now completed. The contractor and Village staff performed a walk-through to identify any areas that need additional work or repairs. The contractor will work on completing these minor items over the next few weeks.

This will be the final Blog Post for the project.

We would like to take this opportunity to thank all the residents for your patience and understanding over the past several months as the construction work was completed.

If you have any additional questions or concerns, please feel free to contact the Village Project Manager, Tim Schwister, at 947-904-4422.

Friday, June 10, 2016

Major Construction Completed!!!

Work Completed Last Week, June 6th to June 10th
·         Paved asphalt surface on roadway
·         Completed asphalt driveway restorations
·         Completed construction of earthen berm along East Lake Avenue
·         Installed arborvitae trees on earthen berm
·         Completed topsoil and sod restorations along project site
·         Complete topsoil, seed, and erosion blanket restoration along vacant properties
·         Village contractor removed 3 dead trees on vacant properties
·         Removed traffic control signage from project site
·         General site clean-up

Work Anticipated to be completed Next Week, June 13th to June 17th  
·         Perform walk through with Village staff to identify any areas that need to be addressed by contractor
·         Complete general clean-up of project site.

Major construction is now completed!!! Village staff and the contractor will walk the site in the coming days to identify any areas that need additional work.

Regarding the landscape restoration, the contractor will continue to water the landscape restoration areas until a healthy stand of grass is established. Any areas that do not survive will be restored by the contractor.

We understand it has been a long process to get to this point. We appreciated all your patience and understanding throughout the construction project. We are hopeful that you are satisfied with the improvements to the neighborhood.

Friday, June 3, 2016

Asphalt Surface Paving this Week

Work Completed Last Week, May 30th to June 3rd
·         Milled existing asphalt surface along Pine Street
·         Performed pavement patching as required along existing roadway
·         Begin construction of earthen berm along East Lake Avenue
·         Replaced guard rail at Pine Point and Church Street
·         Performed final testing of new water main

Work Anticipated to be completed Next Week, June 6th to June 10th  
·         Pave asphalt surface along  entire project site
·         Complete construction of earthen berm along East Lake Avenue
·         Plant trees on earthen berm
·         Sod restorations along Pine Street that were not previously completed
·         Topsoil, seed, and erosion blanket restoration along vacant properties on north end of Pine Street
·         Perform final walk-through with Village staff to determine any outstanding items to be completed.
 
The major construction is nearing a completion with the installation of the final asphalt surface layer scheduled for early next week. We request vehicles are not parked along the street during working hours (7:00 AM to 5:00). Cars may be parked along the street during non-working hours.

On the day of final asphalt surface paving, we also request trips along Pine Street are limited to help facilitate construction and provide a better final product. Once the asphalt is rolled for the final time, vehicles are allowed to drive on the roadway.

The morning of the asphalt surface paving, a thin layer of tack coat (or oil) will be placed on the existing surface. This can be driven over; however, we request you please drive slowly to help prevent the tack coat from getting on your vehicles.

Thanks again for all your patience and understanding throughout the entire construction project. We hope that you are satisfied with the overall project and improvements made to your neighborhood.