·
Competed excavation and installation of aggregate base course within new
cul-de-sac at north end of Pine Street
·
Poured new concrete curb & gutter within new cul-de-sac
·
Installation and final grading of topsoil and installation of sod within
areas disturbed during construction
·
Fence Repairs along East Lake Avenue
·
Trench paving along underground utility improvements
·
First layer of asphalt pavement within cul-de-sac
Work Anticipated to be completed Next Week, May 30th
to June 3rd
·
Mill existing asphalt surface along Pine Street
·
Perform pavement patching as required along existing roadway following
milling operation
·
Pave asphalt surface along entire roadway
·
Construction of earthen berm along East Lake Avenue
·
Replace guard rail at Pine Point and Church Street
Now that the sod restoration, trench paving, and first layer
of asphalt within the new cul-de-sac is completed, the majority of the
disturbed areas are restored. The trench paving and first layer of asphalt
within the cul-de-sac will greatly reduce the amount of dust along the project
site. The sod restoration re-establishes the existing landscape along most of
the homes. The contractor will continue to water the sod until it is fully
established.
Next week the primary focus will be on roadway resurfacing.
The existing roadway will be milled off, leaving a layer of the existing
roadway in-place. Any patching required within the existing asphalt roadway
will be performed. If progress goes as anticipated, the new asphalt surface
will be installed by the end of the week. We ask that residents do not park
their cars along the street during working hours (7:00 AM to 5:00) to help
facilitate construction. On-street parking will be allowed during non-working
hours.
Thanks again for all your understanding regarding the
parking restrictions. The project is nearing completion with only a few major
items of construction remaining to be completed.
No work will be performed over the holiday weekend.
Have a fun and safe Memorial Day Weekend!!!